RMS construction for NATURGAS

Inicio / Portfolio / RMS construction for NATURGAS
RMS construction for NATURGAS

Description Customer and Project

Naturgas has trusted on the experience of NIP, S.A. to execute the “TURN-KEY” construction of one Metering Station and two Regulation and Metering Stations in the ‘NATURGAS ENERGÍA Y TRANSPORTE, S.A.U.’ SECONDARY TRANSPORT GAS PIPELINE SERINYA – FIGUERES:

  • MS G-400 (45 BAR) AT POSITION 01, Serinyá municipality
  • MS G-250 (10 BAR) AT POSITION 02, Navata municipality
  • MS G-1000 (45/5 BAR) AT POSITION 03, Vilafan municipality

Tasks developed

  • Civil Works.
  • Supply and mechanical assembly of the RMS including all the necessary elements.
  • Supply and assembly of the Cathode Protection Station (if applicable).
  • Supply and assembly of the Electrical installation and associated controls.
  • Documentation, tests and commissioning